Question No 22:

At the beginning of the year GHI, had opening work-in-progress of $240,000. During the year, the following expenditure was incurred: $ Prime cost 720,000 Factory/production overheads 72,000 Closing work-in-progress 350,000
What was the factory/production cost of goods completed during?

A.
$538,000
B.
$610,000
C.
$682,000
D.
$902,000

Answer: C